Sunday, May 4, 2014

Quantitative Risk - Expected MonetaryValue or Decision tree analysis

Expected Monetary Value Analysis (EMV)


Expected Monetary Value Analysis or EMV Analysis in short is the 2nd tool and technique in the Quantitative Risk Analysis and Modeling Techniques sub-group.

Expected Monetary Value Analysis calculates the average outcome of future scenarios that may or may not occur. The may or may not occur indicates the fact that, the future scenario is a risk and hence has a probability % based on which it occurs.

EMV Analysis calculates the Monetary Value of the Impact of this scenario if it occurs in future – Today.

Some Points to Remember:

• EMV Analysis is used to make decisions (Ex: Decision Tree Analysis). Don’t worry about Decision Tree Analysis just yet. That is going to be the next chapter
• EMV Analysis looks at both probability and impact together
• When using EMV we must be in a “Risk Neutral” mind-set and not Risk Averse or Risk Seeking. Remember the chapter titled Factors that Influence Risk Communication where we took a look at people and their Risk Attitudes?
• When you have multiple scenarios, you add the EMV of all the possible outcomes together before taking the decision.
• Usually options with higher EMV is the option to you decide on.
• In all cases, a positive EMV indicates that it is an opportunity while a negative EMV indicates a Risk/Threat.

It’s important to remember that the EMV is a type of average. If you were to play the coin-flip game a large number of times under identical circumstances, and make the same decision each time (e.g., to drill oil well or to farm out oil well), then over the long run you would expect to wind up with $12,500 if you choose to drill and $17,500 if you choose to farm out. While the EMV may be useful for gamblers or serial investors, using EMV needs to be done with some care for stand-alone projects in the face of uncertainty.
Formula for Expected Monetary Value:
EMV = Probability * Impact

Some Examples:
Example 1:
Impact of a Risk = $ 10,000
Probability of Risk Occurring = 15%
EMV = Impact * Probability = 10,000 * 15% = $ 1500/-
$1500 is the Expected Monetary Value of this scenario. i.e., if this risk were to materialize, the monetary value of the occurrence will be $1500.

In the exam, it is easily possible that the same question as Example 1 could be worded into a long paragraph to check if you understand the concept. The following example does just that.

Example 2:
Rajesh is the Project Manager for Project A and is doing EMV Analysis. For one of the top-priority risks he can see that the impact will be $10,000 if it occurs. The Risk Register also states that, as per the initial analysis, the probability of this risk materializing is 15%. What would be the Expected Monetary Value of this Risk, if Rajesh decides to perform EMV Analysis?

Can you guess what the Answer will be?

The same $1500. All this question does is, put the camouflage the important details like impact and probability that are required to calculate the final answer along with loads of irrelevant information which can easily confuse a novice Risk Manager.

Example 3:
Project X has a 60% Probability of success with an impact of $50,000 and has a 40% chance of failure with an impact of $-20,000. What is the Expected Monetary Value of this Project?

EMV of success = 50000 * 60% = $ 30,000
EMV of failure = -20000 * 40% = $ -8,000
Total EMV = $ 22,000/-

Trivia:
In all cases, a positive EMV indicates that it is an opportunity while a negative EMV indicates a Risk/Threat.

  • Expected Monetary Value Example for Project Risk Management

    Suppose you are leading a construction project. Weather, cost of construction material, and labor turmoil are key project risks found in most EMVStormconstruction projects:
    • Project Risks 1 - Weather: There is a 25 percent chance of excessive snow fall that’ll delay the construction for two weeks which will, in turn, cost the project $80,000.
    • Project Risks 2 - Cost of Construction Material: There is a 10 percent probability of the price of construction material dropping, which will save the project $100,000.
    • Project Risks 3 - Labor Turmoil: There is a 5 percent probability of construction coming to a halt if the workers go on strike. The impact would lead to a loss of $150,000. Consider your industry and geographic area to determine whether this risk would have a higher probability.
    Next, let's see how to quantify the project risks by calculating the Expected Monetary Value of each risk.


  • In this Expected Monetary Value example, we have two negative project risks (Weather and Labor Turmoil) and a positive project risks (Cost of Construction Material). The Expected Monetary Value for the project risks:

    - Weather: 25/100 * (-$80,000) = - $ 20,000
    - Cost of Construction Material: 10/100 * ($100,000) = $ 10,000
    - Labor Turmoil: 5/100 * (-$150,000) = - $7,500

    Note: Though the highest impact is caused by the Labor Turmoil project risk, the Expected Monetary Value is the lowest. This is because the probability of it occurring is very low.

    This means that if the:
    Weather negative project risks occurs, the project loses $20,000,
    Cost of Construction Material positive project risks occurs, the project gains $10,000, and
    Labor Turmoil negative project risks occurs the project loses $ 7,500

    The project’s Expected Monetary Value based on these project risks is:
    -($20,000) + ($10,000) – ($7,500) = - $17,500

    Therefore, if large number of construction projects like this are done for which  if all these risks occur with same probability and impact, then on an average each project would lose $17,500. In this scenario, the project manager can add $17,500 to the budget to compensate for this. This is a simplistic Expected Monetary Value calculation example.

Decision Tree Analysis

Decision Tree Analysis is used to make decisions based on the risks that could impact us in the various possible scenarios we may encounter in future. It calculates the Expected Future Value of an activity based on the current impact & probability of all risks.

Decision Tree Analysis uses a Decision Tree Diagram. In the tree, we start at the starting point and go through the tree and take a decision based on the EMV for the Alternatives that are available for us. It shows a sequence of inter-related decisions and their respective EMVs so that you can take a good and properly thought-out decision. Decision Tree Analysis is used typically to take decisions dealing with Time or Cost.

Let us now take a look at some examples to understand Decision Tree Analysis:

Example 1: 

Let us say, we are given the task of deciding between Vendor A and Vendor B. Vendor A has a Success Probability of 55% and an Impact of $ 70,000 while there is no impact on Failure. Similarly Vendor B has a 75% probability of Success and has an impact of $ 55,000 and he too has no impact on Failure. Based on this information, how would you choose the Vendor?

The simple Answer would be – Use Decision Tree Analysis. So, based on this question, if I were to create a Decision Tree, it would look like below:



So, here:

EMV for Vendor A: = 70000 * 55% = 38,500

EMV for Vendor B = 55000 * 75% = 41,250



Now, you know the EMV for each vendor. So, the wiser choice would be to choose Vendor B because the Expected Monetary Value of choosing Vendor B is greater than Vendor A.

Trivia:
If we had just considered the Impact, Vendor A would look like a better choice because he has a higher impact. But, he has a lower probability. So, Vendor B, even though has a lower impact, is selected because the combination of both probability and impact makes him the better choice.

Example 2: 

Example 1 was an all positive scenario where there is no Impact for failure. What would you do in an all Negative Scenario?? Look at the Decision Tree Below:



In this example, in both cases, there is no impact if the outcome is a success. But, both Vendors A & B have an impact on failure and have a probability of failure too. So in this case, you may be wondering why I chose Vendor B instead of A, even though the EMV for A is higher. Are you???

In example 1, we were looking at positive EMV (For Success or Profits) so, we chose the vendor with higher profitable EMV. Whereas, in this case we are calculating Negative EMV (For Failure or Losses). So, choosing the vendor who would cause lower losses in case of a failure would be a better choice. Wouldn’t it??

Example 3: In examples 1 & 2, we took a look at trees that either had a positive or negative impact only. What must we do if we have both? Look at the tree below:



In this case, both Vendors A & B have Impact on both Success & Failure. So, the EMV for each vendor is the sum of the Individual EMV’s.

For Vendor A: 

EMV for Failure = 1000 * 30% = 300

EMV for Success = 6000 * 70% = 4200

Total EMV for Vendor A = $ 4,500/-

For Vendor B: 
EMV for Failure = -1200 * 40% = -480

EMV for Success = 7500 * 60% = 4500

Total EMV for Vendor B = $ 4,020/-

So, based on the total EMV, Vendor A is the better choice…

Trivia: 
Did you note that Vendor B has a negative monetary impact in case of failure??? Be careful and note the – sign… If you did the calculation in a hurry and ignore the – symbol, your EMV for Vendor B would’ve been $ 4,980 suggesting that Vendor B is the better choice. Whereas, the truthwas that, because of the –ve impact on failure, Vendor A is the better choice. 
Example 4: 

In all of the examples above, our decision was based solely on the impact and probability of the scenario’s outcome. What must we do in cases where the decision should also take into account the initial expenses incurred for the activity?

Let’s say, your company has grown hugely in the past couple of years and your current office does not have enough space to accommodate the new guys. So, now you have two choices – Either to construct/purchase a new office or expand the current premises to accommodate the newer guys. In either case, there is cost involved in completion of the office premises. Plus, there could be a high demand for the new space which results in high profits or there could be a low demand resulting in lower profits. This scenario is outlined in the Decision Tree below:




In Tree’s where an initial investment is present, we proceed just like the other scenarios wherein we calculate the EMV for each alternative and sum it up. After that, we deduct the Initial Expenses to arrive at the actual monetary value of the alternative.

Trivia: 
In simpler terms, let’s say, I invest 5,000 rupees today and earn 10,000 after 6 months, my profit is 5,000 whereas, if I invest 10,000 rupees and earn 12,000 at the end of 6 months, my profit is only 2,000. Though the eventual money I get at the end of 6 months is higher in the second case, it also means that I invest a larger amount up front thereby reducing profits. So, option 1 where in invest 5000 and get 10000 at the end of 6 months is the better choice. Isn’t it?

So, the EMV Calculation works out as follows:



For Build: 
Total EMV = 522,000

If we include Initial Cost – Net EMV = $ 292,000/-

For Expand:

Total EMV = 393,000

If we include Initial Cost – Net EMV = $ 298,000/-

So, the decision here would be to expand the current office premises. Even though the profits that we may earn if we move to a new office are higher, there is a higher impact if people are not willing to move and a high initial cost. As a result, the EMV of expanding the current office is more profitable and hence it is selected.


Some Important Decision Tree Related Terms: 

For the exam, actually speaking, whatever we have covered so far is more than sufficient. But, for the same of completeness, I want to cover one last topic related to Decision Trees. There are 3 key terms that we will use while using Decision Tree’s in real life. They are:

a. Decision Node – The Point where an action or decision needs to be made – Signified by a solid black square
b. Chance Node – The Point where events that cannot be controlled by the person who is taking the decision happen – Signified by a solid black dot
c. End of Branch - The end point with nothing connected on one end – Signified by a solid tilted Triangle.

The sample Decision Tree below can help you understand better – as to what I am trying to convey here: